Two Storey Side Extension Costs
A typical project like this may require a minimum construction budget of £60,000 - £70,000 + VAT. Our Architectural services can be charged at an Hourly Rate or as a Fixed Price Fee the choice is yours.
An estimate of the fees likely to be charged by other Consultants and Local Authorities is listed here:
Structural Engineer’s Fee = £700 - £900 + VAT
Energy Loss Calculation Fee = £100 + VAT
Ordinance Survey Copyright Licence Fee = £20 - £30
Planning Application Fee to Local Authority= £160
Building Warrant Application Fee to Local Authority= £700
An estimate of the likely timescale for each stage of the process is listed here:
Feasibility Stage = 1 to 3 months
Planning Application Stage = 2 to 4 months
Building Warrant Stage = 2 to 4 months
Pre-Construction Stage = 1 month
Construction Stage = 3 to 4 months
Post-Construction Stage = 1 to 3 months
The prices quoted above are subject to the following conditions: